* Jan. 3- 7: Pre Kick-off Activities lunch time training sessions
* Jan. 8-9: Kick-off Weekend
* Jan. 10-14 Week One - Overall Design
* Jan. 15-21 Week Two - Subsystem Design
* Jan. 22-26: Week Three - Dead Week
* Jan. 26-Feb. 4: Week Four - Assemble Robot
* Feb. 5-12: Week Five -Test
* Feb. 12-20 Week Six - Practice and Prepare Crate
* Feb. 17-22: Week Seven - Ship Robot - Practice and Prepare Crate
* Feb. 23-Mar. 23: Prepare team for competitions
* Mar. 24-26: Los Angeles Regional Competition
* Mar. 31-Apr. 2: Las Vegas Regional Competition
Please click here for a detailed 2011 Robotics Team Schedule
|
|
It's Build Season! We are here 24/7.
|